NZIA
|
ArchitectureNZ
|
The Grad
|
SANNZ
|
Cross Section
|
Shaping Our Places
Overview
APL Sponsor
The Seminar Series
Upcoming GDP Events
Presenters
Overview
NZIA Practice Notes
The Registration Process
The Experience Areas
Case Study
Practical Experience
Have Your Say
Search Forum
About the Forum
Overview
The Forum Advisors
Rules
My Forum
Forum Profile
My Friends
Graduates
Graduate Events
Latest News
Competitions
NZIA
NZIA Events
NZIA News
Competitions
Image Galleries
Hot Links
Contact theGrad
Overview
Image Galleries
Hot Links
Events Listings
Login
Registered Users Sign in Here
Have Your Say
Search Forum
About the Forum
Overview
The Forum Advisors
Rules
My Forum
Forum Profile
My Friends
'the Grad' Forum
Forum Home
»
PROJECT MANAGEMENT
»
F - Contract Administration and Observation
» PC Sum Variation
Search:
PC Sum Variation
Author
Message
MiTch
#1
03-June-2011
(time: 14:23)
Posts: 2
Joined: 03-June-2011
A current job I am administering the contract involves a PC Sum for a custom exterior door. The door has been installed and the contractor has sent me a Variation Price Request asking to increase the PC Sum. Within his VPR he has included a large figure for the labour to install, clad and hang the doors. My question is whether the contractor can claim labour in items described as PC Sums in the contract documents? Section 10 of SCC2009 Conditions of Contract state PC Sums do not include the cost associated with installation?
--------------------------------------------------------------
John Chaplin
#2
04-June-2011
(time: 11:08)
Moderator
Posts: 4
Joined: 15-June-2009
Hi Mitch,
you are right that PC sums do not include the cost associated with labour or installation and is purely for the supply of an item which the selection of or cost was not able to be determined at the time of tender.
The normal course of events is that the contract would allow for the installation of the item unless specifically excluded,especially in the case of a door.
For the supply and labour to have been included then it would / should have been listed as a provisional sum for the supply and installation of the door
The nomination of a PC sum for an entry door is quite common and allows flexibility later to nominate or design a specific type of door, and with such an item the contract would always include the labour to instal.
Further to this, the architect must direct the expenditure of the sum and nominate who is to supply it.
In this case I feel you contractor is having you on.
cheers
John
--------------------------------------------------------------
John Chaplin, Director, Chaplin Crooks Architects
Home
|
Graduate Development Programme
|
NZRAB Registration
| Forum |
Whats Hot
|
Contact
|
My Profile
Have Your Say |
Search Forum
|
About the Forum
|
My Forum
© Copyright NZIA. Please read the
Terms of Use
and
Privacy Policy
.